Insights / Procurement / Palo Alto
RESEAT / Insights / Procurement

Install day: what goes wrong between the warehouse and the floor

The furniture was right, the price was right, and the office still was not usable on Monday. Almost every one of those stories is an installation story.

Procurement
In short

Office furniture installation in the Bay Area fails for logistics reasons far more often than product reasons. The recurring causes are a freight elevator or dock booked too late, a certificate of insurance that does not meet the building's limits, product delivered before the space is ready to receive it, and no named owner for the punch list. Book building access before you book the crew, get the certificate of insurance requirements in writing from both buildings at the start, confirm who receives and inspects the delivery, and agree the punch list process before install day rather than during it.

The furniture selection took four months and three rounds of review. The install took two days and decided whether any of it mattered.

Installation is where furniture projects actually fail, and they fail for boring reasons. Not the wrong chair. A freight elevator booked by somebody else, an insurance certificate short of the building's limits, a delivery that arrived before the floor was ready to take it.

The four failures that account for most of it

The sequence that works

  1. Get both buildings' rules in writing at the start Dock dimensions and hours, freight elevator dimensions and hours, after-hours requirements, COI limits and additional insureds, floor and elevator protection, and whether a waste plan is required for packaging. This is a single email and it prevents most of what follows.
  2. Book the freight window, then everything else In a downtown tower this may be a weekend or a 6pm to 6am shift, and that changes the labor cost. Knowing it early means the budget carries it instead of absorbing it as a surprise.
  3. Decide where product is received Direct to site works when the site is genuinely ready. It usually is not. Receiving and inspecting at a warehouse first means damage is found before it is on your floor, and it means you control the delivery date rather than the manufacturer. See where furniture goes when the new space is not ready.
  4. Sequence by zone, against a marked plan Install in the order the floor will be used, with a plan that labels each zone and each product code. A crew working from an unlabelled drawing makes reasonable guesses that are expensive to undo.
  5. Walk the punch list the same day, with a named owner Before the crew leaves. Recorded, photographed, with a resolution date attached. A punch list raised the following week is a negotiation; one raised on the day is a task.

Receiving is not a formality

The most useful thing a receiving step does is establish when damage happened. Furniture inspected at a warehouse and found damaged is a freight claim. The same furniture found damaged on your floor a week after install is an argument between three parties, and you will lose it, because nobody can prove which of them put the gouge in the credenza.

It also decouples your schedule from the manufacturer's. If the product lands early and the floor is not ready, receiving means that is a storage question rather than a crisis. This applies to second life inventory as much as to new, and it is one of the reasons a short lead time is easier to work with, not harder.

What to have in writing before install day

ItemWho confirms itWhen
Freight elevator and dock bookingProperty managerBefore the crew is scheduled
COI limits and additional insuredsProperty manager, both buildingsAt project start
Site readiness sign-offGC or project managerOne week before delivery
Labelled installation planDesigner or dealerOne week before delivery
Packaging removal and recyclingInstallerIn the proposal, not on the day
Punch list owner and processYouBefore install day

The Peninsula version

Installing in Palo Alto and along the Peninsula is generally easier than downtown San Francisco. Lower buildings, better loading, fewer after-hours restrictions. The constraint that replaces it is scale: a growing Peninsula team is often installing into a space it will reconfigure within eighteen months, which makes the install plan itself worth keeping. A labelled, accurate record of what went where and in what finish is the difference between a reconfiguration and a re-survey, and that is exactly what a RESEAT ID record preserves per piece. The growth pattern is covered in furnishing a team that will change size twice.

Have a move-in date and a building with rules? Send the date, the floor plan, and both buildings' requirements through a design brief and we will build the schedule backwards from the freight window. If a space is being cleared as well as filled, the decommission intake covers the other end.

Questions we get asked

Logistics, not product. The recurring causes are a freight elevator or dock booked too late, a certificate of insurance that does not meet the building's limits, product delivered before the space is ready to receive it, and no named owner for the punch list on install day.

Almost always, and the required limits and additional insureds differ by building. Get the requirements in writing from every building involved at the start of the project, because a certificate that clears one tower can get a truck turned away at the next while the crew still bills for the day.

Only when the site is genuinely ready, which it often is not. Receiving and inspecting at a warehouse first establishes when any damage occurred, which turns a dispute into a freight claim, and it decouples your install date from the manufacturer's delivery date.

The same day, before the crew leaves, with a named owner, photographs, and a resolution date attached to each item. A punch list raised on the day is a task. The same list raised three weeks later is a negotiation between parties who can no longer establish what happened.

Keep reading

Furnishing a space this year?

Tell us what you have or what you need. We come back with a plan, a number, and the impact math to go with it.

Decommission intake Submit a design brief